Project/Completion Year: San Mateo North Segment (Phase I & II) 2019/2022
Customer: Cal Trans District 4
Contractor: Kiewit Infrastructure West Co. / CoatMasters Coatings Installation Group (CCIG) San Mateo 101, (North Segment), concrete surface texture with heavy sandblast on median barriers on a total of 356-set locations. Patterns sandblasted amounted to 8,845 square feet and applied concrete paint to 89-holes x 356-set locations, totaling 31,684 holes on barrier modules after sandblasting.